<=Please edit the table below to plan for Dovetail testing during the PlugFest at Orange=>
the table below shows the dovetail test planning. on each Pod, the CloudOS can be deployed such as Danube and Wind River Titanium 3.
it wil take 2 hours to install the dovetail tool and 1 hour to run that. once the dovetail tool is deployed, it can run several times.
for the end of each day, there will be short summary meeting for the test results revew and feedbacks.
Huawei POD(onsite)(installer: joid) on Tuesday
time slotes | dovetail( owner: hongbo) | scenarioes deployment(owner: Narinder Gupta) |
---|---|---|
8:00-10:00 | Dovetail deployment | (os-nosdn-nofeature-ha) deployment |
10:00-11:00 | Dovetail running | |
? | ||
17:00-18:00 | summary and feedback on Work Area C |
...
Huawei POD(onsite)(installer: joid) on Wensday
time slotes | dovetail(owner: hongbo) | scenarioes deployment(owner:liangqi) |
---|---|---|
8:00-10:00 | Dovetail deployment | (os-nosdn-nofeature-ha) deployment |
10:00-11:00 | Dovetail running | |
11:00-14:00 | Danube 1.0 os-odl_l2-nofeature-ha | |
14:00-15:00 | dovetail running | |
Huawei POD(onsite) on Thursday
time slotes | dovetail(owner: hongbo) | scenarioes deployment(owner:Raineri, Eddy) |
---|---|---|
8:00-10:00 | Dovetail deployment | |
13:00-16:00 |
...
Wind River Titanium 3 based on Mitaka with AVS deployment | ||
16:00-17:00 | dovetail running | |
Intel POD(onsite)(installer: ?) on ?
time slotes | dovetail(owner: hongbo?) | scenarioes deployment(owner: jack) |
---|---|---|
8:00-10:00 | Dovetail deployment | ? |
10:00-11:00 | Dovetail running | |
11:00-14:00 | ? | |
14:00-15:00 | dovetail running | |
15:00-17:00 | ? |
lenovo POD(onsite)(installer: ?) on ?
time slotes | dovetail(owner: ?) | scenarioes deployment(owner: Brahmanand Gorti) |
---|---|---|
8:00-10:00 | Dovetail deployment | ? |
10:00-11:00 | Dovetail running | |
11:00-14:00 | ? | |
14:00-15:00 | dovetail running | |
15:00-17:00 | ? |
Nokia POD(onsite)(installer: apex(Triple-O Danube)) on Monday
time slotes | dovetail(owner: ?) | scenarioes deployment(owner: Rautakumpu, Mika) |
---|---|---|
8:00-10:00 | Dovetail deployment | os-nosdn-nofeature-ha deployment |
10:00-11:00 | Dovetail running | |
11:00-14:00 | ? | |
14:00-15:00 | Dovetail running? | |
15:00-17:00 | ? |
Advantech POD(onsite)(installer: Fuel) on Thursday
time slotes | dovetail(owner: ?) | scenarioes deployment(owner: Eric.vanVliet) |
---|---|---|
8:00-10:00 | Dovetail deployment | os-nosdn-nofeature-ha deployment |
10:00-11:00 | Dovetail running | |
11:00-14:00 | ? | |
14:00-15:00 | ||
15:00-17:00 | ? |
Hardware | VIM+NFVI Software :: Scenario | Installer | Location | Dovetail test plan | |
---|---|---|---|---|---|
Huawei POD | compass: Danube 1.0 os-nosdn-nofeature-ha Danube 1.0 os-odl_l2-nofeature-ha, Colorado 3.0 ? Joid: os-nosdn-nofeature-ha,nosdn-lxd-ha | compass and joid | Onsite | 4/25,4/26 | |
Intel POD | Danube/windriver? | compass?apex?joid? | remote | ||
Nokia POD | Danube 1.0 os-nosdn-nofeature-ha | apex(Triple-O Danube) | onsite | 4/24 | |
Lenovo OCP hardware ( Intel Broadwell CPUS and Mellanox CX4 nics) | Wind River Titanium 3 based on Mitaka with AVS
| compass?apex?joid? | remote | yes, time(TBD) | |
Lenovo OCP hardware ( Intel Broadwell CPUS and Mellanox CX4 nics) | Danube 1.0 | ||||
Wind River lab ( Intel Sandybridge - Intel Xeon-D processors with Niantic and Fortville nics) | Wind River Titanium 3 based on Mitaka with AVS | remote | |||
Wind River lab ( Intel Sandybridge - Intel Xeon- D processors with Niantic and Fortville nics) | Danube 1.0 | ||||
Advantech (Advantech Danube-Plugfest) | Wind River Titanium 3 based on Mitaka with AVS | Fuel | onsite | 4/27(VPN and SFC related scenarioes) | |
Advantech (Advantech Danube-Plugfest) | Danube 1.0 | ||||
Orange | Danube/windriver? | compass?apex?joid? | remote | ||
NEC | Danube/windriver? | compass?apex?joid? | remote | ||
hardware? | windriver | dovetail testing on Thursday(pre-test will be done before the dovetail testing. (provide own hardware) |
...