For the August Governing Board meeting, we need to cover 3 specific areas (the first two three headings below, and ???). Additional material has also been captured.
...
- Continue "Working Upstream": Open Stack, CNCF, other LFN projects (FDIO, ODL, ONAP, ...), ETSI NFV, IETF, others
Approximate Timeline
Factors:
- Governing Board Decision in October 2020?
- OPNFV JERMA meta-Release Calendar: December 2020 Release date
- CNTT Baraque Release in September 2020 (insert additional releases planned...)
- Current CNTT officer term ends in December 2020
- Intermediate tasks to flesh-out, post GB decision, such as the structure of the new organization
- Nomination periods and Elections take about 6 weeks - propose to start the Election Calendar in November 2020 (half of December is unavailable).
- NewName selection: Community and Marketing
Estimate: New org in operation in January 2021
Goals for this Option/Description
...