MilestonesFeb 2017March 2017April 2017May 2017June 2017July 2017

NOTE: Milestones below do NOT mean project tasks

are sequential.

 Most will be in progress in parallel.

Preparation     

(M1)

High level plan of Dovetail completed & reviewed by TSC/Board,

 C&C addendum completed, reviewed, ready for decision.

 March 3&10 - completed in Dovetail
March 6 - review with C&C
March 14 - TSC review
March 20 - Final C&C, to Board
    

(M2)

Plan in Jira with epics defined & owners assigned.

 Expected completion dates committed.

 March 24    

(M3)

Dovetail tool software available for Alpha testing by volunteers

in Pharos and/or vendor and/or third party tester labs.

(Note: this can be using Colorado without dependency with

Danube or finalized test plan.)

 March 31    

(M4)

CVP review/approval

  April 3-6
(ONS)
   

(M5)

Test strategy details reviewed, finalized and documented.

 Test tool migrated to Danube, all design decisions finalized,

Tool software completed in a CI for validation.

Demo/review in PlugFest.

All open decision points closed/finalized.

  

April 24-28

(PlugFest/HackFest)

   

(M6)

Test areas and Test cases list ( i.e. the CVP test suite) finalized.

 Dovetail software linked with the right test suite and frozen.

Draft user docs completed.

Bug fixes only from this point on.

   May 26  

(M7)

Beta ready. Test suite/software/doc beta ready.

 LF/C&C/workflow and tools in place.

The test suite and tool presentation/demo in OPNFV Summit.

CVP announcement.

Tutorials.

    June 12-16
(OPNFV Summit)
 

(M8)

User trial by vendors and test labs completed.

 Feedbacks/bugs collected. Final bug JIRA tickets.

    June 30 

(M9)

Final release of all deliverable

     July 14

(M10)

CVP launch

     end of July
       
       

...