MilestonesFeb 2017March 2017April 2017May 2017June 2017July 2017

NOTE: Milestones below do NOT mean project tasks

are sequential.

 Most will be in progress in parallel.

Preparation     

(M1)

High level plan of Dovetail completed & reviewed by TSC/Board,

 C&C addendum completed, reviewed, ready for decision.

 March 3&10 - completed in Dovetail
March 6 - review with C&C
March 14 - TSC review
March 20 - Final C&C, to Board
    

(M2)

Plan in Jira with epics defined & owners assigned.

 Expected completion dates committed.

 March 24    

(M3)

Dovetail tool software available for Alpha testing by volunteers

in Pharos and/or vendor and/or third party tester labs.

(Note: this can be using Colorado without dependency with

Danube or finalized test plan.)

 March 31    

(M4)

CVP review/approval

  April 3-6
(ONS)
   

(M5)

Test strategy details reviewed, finalized and documented.

 Test tool migrated to Danube, all design decisions finalized,

Tool software completed in a CI for validation. (2 installers)

Server side workfow draft system ready for test

Demo/review in PlugFest.

All open decision points (except test case review) closed/finalized.

  

April 24-28

(PlugFest/HackFest)

   

(M6)

Test areas and Test cases list ( i.e. the CVP test suite) finalized.

 Dovetail software linked with the right test suite and frozen.

Draft user docs completed.

Bug fixes only from this point on.

 C&C addendum completed, reviewed, ready for decision.

   May 26  

(M7)

Beta ready. Test suite/software/doc beta ready.

 LF/C&C/workflow and tools in place.

The test suite and tool presentation/demo in OPNFV Summit.

CVP announcement.

Tutorials.

    June 12-16
(OPNFV Summit)
 

(M8)

User trial by vendors and test labs completed.

 Feedbacks/bugs collected. Final bug JIRA tickets.

    June 30 

(M9)

Final release of all deliverable

     July 14

(M10)

CVP launch

     end of July
       
       

...