Revision: r4draft
Change Log
Date | Revision | Event / Change | Milestones Affected | Notes |
---|---|---|---|---|
Apr 19 | r4 | TSC approved revised schedule | M3, M4, M4-S | M3 slips two weeks. M4 and M4-S slip one week. Signoff stays the same. |
Mar 29 | r3 | TSC approved change to release process | M3, M4, M4-S |
| Feb 1 | r2 | TSC approved M1 | M1 | Dec 15 | r2 | Updated events, and Lakelse Sign Off | None | Dec 14 | r1 | Approved by the TSC | all |
Dec 14 | r1 | second draft | M0, M1 | Moved kickoff to Jan 11 and M1 to Feb 1 |
Nov 1TBD | Initial draft | All |