M5
- Final documentation completed
- RI cookbook completed
- Remaining Jira issues assigned to the release closed or pushed to next release
- Prepare release artifacts
- Tag the version of artifacts to be released
- releng job updated to use release branch instead of master
- Release manager collects artifact references from PTLs and communicates those to releng
- Releng moves artifacts to hosting location and provides URLs to RM
- RM verifies URLs
- RM provides confirmed URL list to website manager (aka Brandon) for publication on the website
- Standalone project testing completed
- Release content finalized
- Creation and submission of marketing highlights
- RC1+2 same functional scope, only version updates
- Finalize version numbering for RM, RA1, RA2 – PTL of each needs to complete this task.
- Fix the comment from Pankaj in pull/3077 and rebase
- Traceability matrix updated
Notes on M5