M5

  •  Final documentation completed
  •  RI cookbook completed
  •  Remaining Jira issues assigned to the release closed or pushed to next release Prepare release artifacts
    • Tag the version of artifacts to be released
      •  releng job updated to use release branch instead of master
    • Release manager collects artifact references from PTLs and communicates those to releng
    • Releng moves artifacts to hosting location and provides URLs to RM
    • RM verifies URLs
    • RM provides confirmed URL list to website manager (aka Brandon) for publication on the website
  •  Standalone project testing completed
  •  Release content finalized
  •  Creation and submission of marketing highlights
  •  Finalize version numbering for RM, RA1, RA2
  •  Traceability matrix updated

Notes on M5

M4-S

  •  Proofreading completed. 

Notes on M4-S

M4

  •  RI validation testing completed. The lead for each RI presents the validation plan and results to the TSC.
  •  Proofreading completed.  High priority Jira issues resolved (closed or assigned to future release)
  •  Specification content created matching high level issues (M2) (Note: moved from M3, per TSC agreement Mar 29, 2022)
    •  Workstream leads review PR status with TSC
    •  PRs indicated as closed on the specification dashboard

Notes on M4

  • Specification content created - moved from M3
  •  RC1 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)

M3

  •  RC2 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)
  •  High priority Jira issues resolved (closed or assigned to future release)
  •  Preliminary documentation completed (confirmed by DOCs team) RI1 development completed (confirmed by workstream lead)
  •  RI2 development completed (confirmed by workstream lead) Specification content created matching high level issues (M2)
    •  Workstream leads review PR status with TSC
    •  PRs indicated as closed on the specification dashboard

Notes on M3

M2

  •  RC1 - ready to begin validation testing (statement in TSC meeting or email to TSC list)
  •  RC1 - coverage of RA specified
  •  RC2 - ready to begin validation testing (statement in TSC meeting or email to TSC list)
  •  RC2 - coverage of RA specified
  •  Jira issues assigned to release for each participating project (should reflect work described in project release plan)
  •  High level issues identified by specification team and appear on dashboard.

Notes on M2

M1

Notes on M1