Anuket Project
Red River Schedule
Milestone | Description | Delta in weeks | Date |
---|---|---|---|
M0 | Start of release | 0 | May 8, 2025 |
M1 | Release Definition | M0 + 2w | May 22, 2025 |
M2 | Scope Freeze | M1 + 2w | Jun 5, 2025 |
M3 | RC Validation Testing | Aug 28, 2025 | |
M4 | RI Validation Testing / Content Freeze | M3 + 5w | Oct 2, 2025 |
M4-S | Proofreading | M4 + 1w | Oct 9, 2025 |
M5 | Release Readiness | M4-S + 4w | Nov 6, 2025 |
Change Log
Date | Revision | Event / Change | Milestones Affected |
---|---|---|---|
Feb 20, 2025 | 1 | Creation of first draft | M0 - M5 |
Apr 9, 2025 | 2 | Update based on Quinnipiac M5 | M0 - M2 |
May 8, 2025 |
| Update based on Quinnipiac M5 | M0 - M5 |