OPNFV TSC Meeting 2020-07-14

Anuket Project

OPNFV TSC Meeting 2020-07-14

Date

Jul 14, 2020 

Attendees

  • @Sridhar Rao

  • @Former user (Deleted)

  • @Georg Kunz

  • @Trevor Cooper

  • @Al Morton

  • @Mark Beierl

  • @Qiao Fu

Absent

  • @Cédric Ollivier

  • @Frank Brockners

  • @Sunku Ranganath (Deactivated)

  • @Cristina Pauna

  • @Dan Xu

  • @Former user (Deleted)

  • @Former user (Deleted)

Non TSC Attendees

@David McBride



Agenda items

Time

Items

Presenter

Notes

Time

Items

Presenter

Notes

5 min

Meeting Logistics

Agenda Bashing
Attendance/Quorum (7)
Approval of Meeting Minutes: Agenda - 2020-06-30 and Meeting Minutes

@Al Morton



5 min

Announcements

Election announcement - 2020 OPNFV TSC Election Nominations
TSC member resignation - 12 seats occupied, 15 available
Vice-Chair and SPC nomination period announcement -  begin Jul 1, 2020 and end Jul 15, 2020 
LFN Operations Survey - please participate

@Al Morton

Does the TSC agree to start an Nomination period for the Vacated and unoccupied 2020-21 TSC Seats?

#agreed

15 min

OPNFV Release Process

Status

@Al Morton

@David McBride

Partial list of issues discussed:

  1. Project Candidates: RI-2 Instantiation, VSPERF, Airship, Prox/SampleVNF, CIRV, would participate in Integration testing, need to talk about others.

  2. Can TSC create the Requirements SC or WG?  (Charter says YES)

  3. Is OPNFV Releasing a Conformance Test Suite? (traceability to CNTT) 

  4. Is this Process for the JERMA Release? (yes)

  5. Are the Definitions of Gates clear?

    1. Testing of the CNTT-selected RC Test Cases

    2.  projects must pass Gating (s 17)

    3. Gates need to be established, install without errors, simple functional tests, success of more advanced features and automated with X-testing

  6. Pre-requisites, include Integration TEST project (Morgan in ONAP), test what OPNFV delivers. OPNFV needs to Release and Support tests that are reliable.

    1. "Establish" items are the key steps for TSC: Requirements Vetting and Integration Test SCs





5 min

CNTT Engagement status updates

CNTT Future Mode of Operation - deadline is September for a recommendation to the Governance Board.

@Jim Baker @Scot Steele

@Scot Steele to provide feedback from LFN GB meeting

10 min

CNTT Engagement  – Future Work Items

Reference Infrastructure and Reference Conformance work with CNTT

@Jim Baker

  • OPNFV 2.0 on hold during CNTT FMO discussion

  • No update on staffing proposal

  • Field test - Orange is doing test (is good)

  • RI/RC conformance - no update

  • CNTT Requirements - engagement based on test cases

  • CIRV mandate review - can drop?

    • Yes, there does not appear to be any interest in CIRV so we can remove this from the agenda.



2 min

OVP Engagement status update

Performance testing discussion status update

@Al Morton

@Trevor Cooper

  • VDTF Session on Performance testing with OVP 2.0 went well

  • Representation needed at bi-weekly OPV meeting - see notes page for more info

  • current page (same as above?)

2 min

OPNFV Project Reviews

Projects:

@Jim Baker



10 min

Status Updates

Program management - website cleanup: https://wiki.opnfv.org/x/jAFbAw
LF IT/Infra update: (Aric GardnerTrevor Bramwell)

@Former user (Deleted)
@Jim Baker
@Trevor Bramwell



5 min

Future Topics

Future Topic: new template for staffing task & requirement evaluation - similar to Intern projects @Mark Beierl
Future Topic: Yardstick's future??  HA test cases.  Bottlenecks' Stress test spawns VMs till it breaks in OVP