Lakelse Release Progress
M5
Final documentation completed
RI cookbook completed
Remaining Jira issues assigned to the release closed or pushed to next release
Prepare release artifacts
Standalone project testing completed
Release content finalized
Creation and submission of marketing highlights
Finalize version numbering for RM, RA1, RA2
Traceability matrix updated
M4
RI validation testing completed. The lead for each RI presents the validation plan and results to the TSC.
Proofreading completed.
High priority Jira issues resolved (closed or assigned to future release)
Notes on M4
RI1 is unsupported per TSC agreement at M1
RI2 validation is ambiguous since we have not yet established criteria
M3
RC1 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)
RC2 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)
High priority Jira issues resolved (closed or assigned to future release)
Preliminary documentation completed (confirmed by DOCs team)
RI1 development completed (confirmed by workstream lead)
RI2 development completed (confirmed by workstream lead)
Specification content created matching high level issues (M2)
Workstream leads review PR status with TSC
PRs indicated as closed on the specification dashboard
Notes on M3
RI1 is unsupported per TSC agreement at M1
M2
RC1 - ready to begin validation testing (statement in TSC meeting or email to TSC list)
RC1 - coverage of RA specified
RC2 - ready to begin validation testing (statement in TSC meeting or email to TSC list)
RC2 - coverage of RA specified
Jira issues assigned to release for each participating project (should reflect work described in project release plan)
Software development team review of RA1 completed. GitHub issues submitted.
Software development team review of RA2 completed. GitHub issues submitted (Lakelse RA2 Review)
High level issues identified by specification team and appear on dashboard.
Notes on M2
The team determined that RA1 had been reviewed sufficiently last fall and that there have not been many changes, therefore, the review of RA1 was skipped in favor of spending the time available on reviewing RA2.
M1
RC Workstream lead(s) recommend RM and RA versions to the TSC for use in the release
RI workstream lead(s) recommend RM and RA versions to the TSC for use in the release
Release string "Lakelse Release" created in Jira (already done)
Release string "Lakelse Release" created in GitLab
Release milestone dates added to GitLab
Notes on M1
Approved by TSC on July 13 with acknowledgment that there is no support for RI1 in Lakelse.