You may subscribe to the meeting and get meeting logistics here.
Apr 23, 2021
Attendees:
Agenda:
- Review Release Process Milestone Planning and resolve issues
- Determine processes for milestone criteria
Notes:
- Text
Apr 16, 2021 (CANCELED)
Apr 9, 2021
Attendees: David McBride, Ildiko , Pankaj.Goyal Gergely Csatari, Al Morton, James Gu
Agenda
- Review Release Process Milestone Planning and resolve issues
- Determine processes for milestone criteria
Notes
- Text
Apr 2, 2021 (CANCELED)
Attendees: David McBride,
Agenda
- Review Release Process Milestone Planning and resolve issues
Notes
- Text
Mar 26, 2021
Attendees: David McBride, Al Morton, Karine Sevilla, Olivier Smith, Karine Sevilla
Agenda
- Review Release Process Milestone Planning and resolve issues
Notes
- Reviewed comments in red from Pankaj.Goyal
- Clarified that the milestone table only indicates criteria for meeting the milestone (i.e., tasks finished), not how the activities are accomplished, or when they start. Those will be determined separately.
- Karine Sevilla suggested adding a task to finalize spec version numbering for M5.
- Al Morton suggested changing the M1 milestone name from "Release Planning" to "Release Definition".
- After above changes, milestone plan is at V .19.
Table of Contents | ||
---|---|---|
|