Anuket Project
Release Process Milestone Planning
CNTT Elbrus release planning (for reference)
Proposed milestones
Note: this table is ONLY intended to identify criteria for the milestones (i.e., a checklist to determine whether the milestone has been reached). It does not speak to how these items will be done, or when they will be initiated. Those will be determined separately.
Milestone | Description | Software Criteria | Software Processes | Specification Criteria (adapted from Elbrus release) | Specification Processes | Delta | Notes |
|---|---|---|---|---|---|---|---|
M0 | Start of release | None | None | ||||
M1 | Release Definition |
|
|
| High Level Scope
RC
| M0+4w | |
Release schedule approved (Release manager prepares schedule and presents to TSC for feedback and approval) | |||||||
M2 | Scope Freeze |
| RC Readiness
JIRA issues
|
| Software development review of specifications
High Level issues created in GitHub
| M0+14w | |
M3 | Code: RC Validation Testing Spec: Content Freeze |
| RC validation testing
High priority Jira issues resolved
Preliminary documentation
RI development is completed
|
| Content created matching issues
| M0 + 18w | |
M4 | Code: RI Validation Testing Spec: Proofreading |
| RI validation testing completed
High priority Jira issues resolved
|
| Proofreading
| M0+22w | |
M5 | Release Readiness |
| Final documentation
RI Cookbook
Jira cleanup
Release artifacts
|
| Traceability Matrix (RI=>RA, RC=>RA, RA=>RM)
| M0+25w | |
Marketing highlights page completed | |||||||
M6 | Release |
|
| M0+26w | |||
Notes from release process discussion at weekly technical meeting (March 15, 2021): Anuket Weekly Technical Discussions - 2021.03.15#Releasemilestones(M1)-Releaseplanning-
Schedule Proposal for June Release (compressed to 16 w)
Milestone | Date | Notes |
|---|---|---|
M0 | Mar 10, 2021 | |
M1 | Mar 30, 2021 | |
M2 | May 11, 2021 | |
M3 | Jun 1, 2021 | |
M4 | Jun 15, 2021 | |
M5 | Jun 22, 2021 | |
M6 | Jul 1, 2021 |
Notes
Attendees: David, Al, Jim, Trevor
Plan for set of milestones for software development, since we have agreed that specifications and software will use different cadences.