Approved Revision:  r1.  Approved by TSC on  


Change Log

DateEvent / ChangeMilestones AffectedNotes

 

TSC approved a two-week slip to M3M3No other milestones affected

 

TSC conditionally approved M2M2Conditioned on a review of the traceability matrix

 

TSC approved M1M1

TSC acknowledged that RI1 is unsupported for Lakelse.  

Although M1 was approved two weeks after the scheduled date, the TSC agreed with the RM recommendation to keep the remainder of the schedule as is with no slip.

 

TSC approved initial scheduleAll




...