Lakelse Schedule

Anuket Project

Lakelse Schedule

Revision:  r2.  Approved by TSC on Nov 16, 2021 



Change Log

Date

Event / Change

Milestones Affected

Notes

Date

Event / Change

Milestones Affected

Notes

Jan 6, 2022 

TSC approved Sign Off

Sign Off

Email vote

Nov 30, 2021 

TSC approved M4

M4



Nov 16, 2021 

Uploaded r2

M4, M5,
Sign Off

New schedule to reflect schedule slip approved by TSC.  Also added dates for January Dev & Test Forum.

Nov 16, 2021 

TSC approved a slip to the remaining schedule 

M4, M5,
Sign Off

This was done to accommodate ongoing issues with RI2 (see meeting notes).

Nov 9, 2021 

PR Review with TSC

M3

This satisfied the conditional approval of M3.

Nov 2, 2021

TSC conditionally approved M3

M3

Conditioned on Specification Team reviewing PRs with TSC

Oct 12, 2021 

TSC approved a two-week slip to M3

M3

No other milestones affected

Aug 31, 2021 

TSC conditionally approved M2

M2

Conditioned on a review of the traceability matrix

Jul 13, 2021 

TSC approved M1

M1

TSC acknowledged that RI1 is unsupported for Lakelse.  

Although M1 was approved two weeks after the scheduled date, the TSC agreed with the RM recommendation to keep the remainder of the schedule as is with no slip.

Jun 1, 2021 

TSC approved initial schedule

All