M5

  •  Final documentation completed
  •  RI cookbook completed
  •  Remaining Jira issues assigned to the release closed or pushed to next release
  •  Prepare release artifacts
    •  Tag the version of artifacts to be released
      •  releng job updated to use release branch instead of master
    •  Release manager collects artifact references from PTLs and communicates those to releng
    •  Releng moves artifacts to hosting location and provides URLs to RM
    •  RM verifies URLs
    •  RM provides confirmed URL list to website manager (aka Brandon) for publication on the website
  •  Standalone project testing completed
  •  Release content finalized
  •  Creation and submission of marketing highlights
  •  Finalize version numbering for RM, RA1, RA2
  •  Traceability matrix updated

M4

  •  RI validation testing completed. The lead for each RI presents the validation plan and results to the TSC.
  •  Proofreading completed. 
  •  High priority Jira issues resolved (closed or assigned to future release)

...