Kali release milestones are tabulated below. For suggested detail  on any milestone, see Release process milestone planning 



Date*Software DevelopmentReference Specifications
M0

 


Start of release
M1

 

~completed version of the template for project plansRelease planning
M2

 

Jira Issues with Fix Version = Kali Release (So M1 and M2 collapse to May 11, if calendar approved on that date)Scope Freeze
M3

 

High Priority JIRA issues resolved and documentation started for new features. Testing for M4 can begin.

Declare for Supplementary Release, if needed.

Content Freeze
M4

 

RC and RI independent and combined testing continue/commenceProofreading
M5

 

Documentation completed

RI cookbook completed, Manifest completed

Remaining Jira issues (assigned to the Kali Release) are closed or pushed to next release

Release artifacts prepared

Standalone project testing completed

Release Readiness
M6

 

Release

Announcement by Marketing

Release

Announcement by Marketing

M7TBDSupplementary Release (if needed)

Date* = date listed , or release calendar approval date.

...