Attendees:

...

  • Antitrust notices
  • Next meetings: bi-weekly starting from 21st of July until September (eg skip 28/7)
  • Moselle
    • all closed
  • Nile
    •  Milestones:
      • M1 Release Definition - August 16, 2022
      • M2 Scope Freeze - September 13, 2022
      • M4 Content Freeze - November 22, 2022
      • M4-S Proofreading - December 06, 2022
      • M5 - Release Readiness + Sign-off - December 13, 2022
    • finished planning dashboard: Nile Specification Planning Dashboard

      • milestone 1 passed
      • Milestone 2 pushed to 13th of September - detailed definition of the issues
    • Fixed author and copyright of conf.py - PR 3123
    • Sorted kanban for RA2 issues - all Nile issues now in to-do and relabelled
      • Ready for M2 - probably

Reference Architecture 2

...