Anuket Project
2022-08-18 - [Anuket RA2] - Meeting Agenda and Minutes
Attendees:
- Riccardo Gasparetto (Vodafone)
- Karine Sevilla
Agenda and Minutes:
- Antitrust notices
- Next meetings: bi-weekly starting from 21st of July until September (eg skip 28/7)
- Moselle
- all closed
- Nile
- Milestones:
- M1 Release Definition - August 16, 2022
- M2 Scope Freeze - September 13, 2022
- M4 Content Freeze - November 22, 2022
- M4-S Proofreading - December 06, 2022
- M5 - Release Readiness + Sign-off - December 13, 2022
finished planning dashboard: Nile Specification Planning Dashboard
- milestone 1 passed
- Milestone 2 pushed to 13th of September - detailed definition of the issues
- Fixed author and copyright of conf.py - PR 3123
- Sorted kanban for RA2 issues - all Nile issues now in to-do and relabelled
- Ready for M2 - probably
- Milestones:
Reference Architecture 2
- AOB & Project review
- Permanent FYI
- CNF Working Group within CNCF - https://docs.google.com/document/d/1YFimQftjkTUsxNGTsKdakvP7cJtJgCTqViH2kwJOrsc/edit
- Actions/Next steps