M5
- Final documentation completed
- RI cookbook completed
- Remaining Jira issues assigned to the release closed or pushed to next release
- Prepare release artifacts
- Tag the version of artifacts to be released
- releng job updated to use release branch instead of master
- Release manager collects artifact references from PTLs and communicates those to releng
- Releng moves artifacts to hosting location and provides URLs to RM
- RM verifies URLs
- RM provides confirmed URL list to website manager (aka Brandon) for publication on the website
- Tag the version of artifacts to be released
- Standalone project testing completed
- Release content finalized
- Creation and submission of marketing highlights
- Finalize version numbering for RM, RA1, RA2
- Traceability matrix updated
M4
- RI validation testing completed. The lead for each RI presents the validation plan and results to the TSC.
- Proofreading completed.
- High priority Jira issues resolved (closed or assigned to future release)
Notes on M4
- RI1 is unsupported per TSC agreement at M1
- RI2 validation is ambiguous since we have not yet established criteria
M3
- RC1 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)
- RC2 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)
- High priority Jira issues resolved (closed or assigned to future release)
- Preliminary documentation completed (confirmed by DOCs team)
- RI1 development completed (confirmed by workstream lead)
- RI2 development completed (confirmed by workstream lead)
- Specification content created matching high level issues (M2)
- Workstream leads review PR status with TSC
- PRs indicated as closed on the specification dashboard
...