This page contains a proposal to modify the Anuket release milestone criteria to support Anuket releases without a dedicated Release Manager.
Milestone | Original criteria | Proposed criteria |
---|
M0 |
| - Release milestones are defined by a volunteer TSC member
- Release milestones approved by the TSC
|
M1 | | - Release string "Orinoco Release" created in Jira by a volunteer TSC member or LF staff
- Release string "Orinoco Release" created in GitHub by a volunteer TSC member or LF staff
- Release milestone dates added to GitHub by a volunteer TSC member or LF staff
- PTLs of non specification sub-projects submit project-level release plans if they plan to participate in the release
- PTLs of specification sub-projects complete specification planning template for the release
|
M2 | - RC2 - ready to begin validation testing (statement in TSC meeting or email to TSC list)
- RC2 - coverage of RA specified
- Jira issues assigned to release for each participating project (should reflect work described in project release plan)
- High level issues identified by specification team and appear on dashboard.
| - For non specification sub-projects participating in the release Jira issues assigned to release (should reflect work described in project release plan) by the PTL-s and reported to the TSC in a mail
- High level issues identified by specification sub-project teams and appear on the GitHub dashboard by the PTL-s and reported to the TSC in a mail
|
M3 | - RC2 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)
- High priority Jira issues resolved (closed or assigned to future release)
- Preliminary documentation completed (confirmed by DOCs team)
- RI2 development completed (confirmed by workstream lead)
| - For non specification sub-projects participating in the release high priority Jira issues resolved (closed or assigned to future release)
- For non specification sub-projects participating in the release preliminary documentation completed (confirmed by )
|
M4 | - RI validation testing completed. The lead for each RI presents the validation plan and results to the TSC.
- High priority Jira issues resolved (closed or assigned to future release)
- Software projects create release branch
- Specification content created matching high level issues (M2) (Note: moved from M3, per TSC agreement Mar 29, 2022)
- Workstream leads review PR status with TSC
- PRs indicated as closed on the specification dashboard
| - Non specification sub-projects have a release branch created by a committer of the sub-project or LF staff
- Specification content created matching high level issues (M2)
- Specification sub-project leads review PR status with TSC
- PRs indicated as closed on the specification dashboard
|
M4-S | | |
M5 | - Final documentation completed
- RI cookbook completed
- Remaining Jira issues assigned to the release closed or pushed to next release
- Prepare release artifacts
- Tag the version of artifacts to be released
- releng job updated to use release branch instead of master
- Release manager collects artifact references from PTLs and communicates those to releng
- Releng moves artifacts to hosting location and provides URLs to RM
- RM verifies URLs
- RM provides confirmed URL list to website manager (aka Brandon) for publication on the website
- Standalone project testing completed
- Verify that there are no unmerged patches
- Release content finalized
- Creation and submission of marketing highlights
- Finalize version numbering for RM, RA1, RA2
- Traceability matrix updated
| - Final documentation completed
- For non specification sub-projects the remaining Jira issues assigned to the release closed or pushed to next release by the PTL-s. Movement of the issues reported to the TSC in a mail or in a TSC meeting.
- Prepare release artifacts
- Tag the version of artifacts to be released
- releng job updated to use release branch instead of master
- PTLs collect all artifact references and communicates them to LF staff
- LF staff moves artifacts to hosting location and provides URLs to the PTL-s and the TSC
- PTL-s verify URLs
- PTL provides confirmed URL list to LF staff and the TSC for publication on the website
- PTL-s verify that there are no unmerged patches or PR-s. In case of any unmerged patches or PR-s notify the TSC.
- A volunteer TSC member or LF staff creates release branch for GitHub
- PTL-s create sub-project specific release highlights and report the creation to the TSC
- TSC drafts release announcement blog post and sends it to LF staff for publication
- TSC member finalizes version numbering for the specification projects
|