M5
Final documentation completed
RI cookbook completed
Remaining Jira issues assigned to the release closed or pushed to next release
Prepare release artifacts
Standalone project testing completed
Verify that there are no unmerged patches
Release content finalized
Creation and submission of marketing highlights
Finalize version numbering for RM, RA1, RA2
Traceability matrix updated
Notes on M5
M4-S
Proofreading completed.
Notes on M4-S
M4
RI validation testing completed. The lead for each RI presents the validation plan and results to the TSC.
High priority Jira issues resolved (closed or assigned to future release)
Software projects create release branch
Specification content created matching high level issues (M2) (Note: moved from M3, per TSC agreement Mar 29, 2022)
Workstream leads review PR status with TSC
PRs indicated as closed on the specification dashboard
Notes on M4
M3
RC2 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)
High priority Jira issues resolved (closed or assigned to future release)
Preliminary documentation completed (confirmed by DOCs team)
RI2 development completed (confirmed by workstream lead)
Notes on M3
M2
RC2 - ready to begin validation testing (statement in TSC meeting or email to TSC list)
RC2 - coverage of RA specified
Jira issues assigned to release for each participating project (should reflect work described in project release plan)
High level issues identified by specification team and appear on dashboard.
Notes on M2
M1
RC Workstream lead(s) recommend RM and RA versions to the TSC for use in the release
RI workstream lead(s) recommend RM and RA versions to the TSC for use in the release
Release string "Nile Release" created in Jira
Release string "Nile Release" created in GitHub
Release milestone dates added to GitHub