Nile Release Progress
Anuket Project
Nile Release Progress
David McBride
Scot Steele
Owned by David McBride
M5
- Final documentation completed
- RI cookbook completed
- Remaining Jira issues assigned to the release closed or pushed to next release
- Prepare release artifacts
- Tag the version of artifacts to be released
- releng job updated to use release branch instead of master
- Release manager collects artifact references from PTLs and communicates those to releng
- Releng moves artifacts to hosting location and provides URLs to RM
- RM verifies URLs
- RM provides confirmed URL list to website manager (aka Brandon) for publication on the website
- Tag the version of artifacts to be released
- Standalone project testing completed
- Verify that there are no unmerged patches
- Release content finalized
- Creation and submission of marketing highlights
- Finalize version numbering for RM, RA1, RA2
- Traceability matrix updated
Notes on M5
M4-S
- Proofreading completed.
Notes on M4-S
M4
- RI validation testing completed. The lead for each RI presents the validation plan and results to the TSC.
- High priority Jira issues resolved (closed or assigned to future release)
- Software projects create release branch
- Specification content created matching high level issues (M2) (Note: moved from M3, per TSC agreement Mar 29, 2022)
- Workstream leads review PR status with TSC
- PRs indicated as closed on the specification dashboard
Notes on M4
M3
- RC2 - RC workstream lead confirms successful completion of validation test plan (statement in TSC meeting or email to TSC list)
- High priority Jira issues resolved (closed or assigned to future release)
- Preliminary documentation completed (confirmed by DOCs team)
- RI2 development completed (confirmed by workstream lead)
Notes on M3
M2
- RC2 - ready to begin validation testing (statement in TSC meeting or email to TSC list)
- RC2 - coverage of RA specified
- Jira issues assigned to release for each participating project (should reflect work described in project release plan)
- High level issues identified by specification team and appear on dashboard.
Notes on M2
M1
- RC Workstream lead(s) recommend RM and RA versions to the TSC for use in the release
- RI workstream lead(s) recommend RM and RA versions to the TSC for use in the release
- RC validation plan created or updated
- RI validation plan created or updated
- Release string "Nile Release" created in Jira
- Release string "Nile Release" created in GitHub
- Release milestone dates added to GitHub
- PTLs submit project-level release plans
- Workstream leads complete specification planning template for release
- RC workstream leads propose plan for RC development (based on an updated RA)
Notes on M1
Related content
Moselle Release Progress
Moselle Release Progress
More like this
Orinoco Release Progress
Orinoco Release Progress
More like this
Lakelse Release Progress
Lakelse Release Progress
More like this
2022-08-18 - [Anuket RA2] - Meeting Agenda and Minutes
2022-08-18 - [Anuket RA2] - Meeting Agenda and Minutes
More like this
2022-03-07- [Anuket RA-1]- Workstream Meeting Agenda and Minutes
2022-03-07- [Anuket RA-1]- Workstream Meeting Agenda and Minutes