Nile Schedule
Revision: r3
Change Log
Date | Revision | Event / Change | Milestones Affected |
---|---|---|---|
08/09/22 | r3 | TSC approved moving M2 one week to Sept 13 to avoid conflict with the Labor Day holiday in the U.S. | M2 |
08/02/22 | r2 | Corrected copy-and-paste error on schedule and added CNCF Telecom Day. | None |
06/14/22 | r1 | The TSC approved the schedule. | All |
06/14/22 | r1 | Second draft. Note: M5 and Sign Off are now merged into a single milestone. This was discussed at the June 7 TSC meeting. | All |
05/10/22 | Initial draft | All |