Anuket Project
Moselle Schedule
Revision: r5
Change Log
Date | Revision | Event / Change | Milestones Affected | Notes |
|---|---|---|---|---|
June 21 |
| The TSC approved M4-S, M5, and Sign Off | M4-S, M5, Sign Off |
|
June 14 |
| TSC deferred M4-S, M5, and Sign Off to June 21 | M4-S, M5, Sign Off |
|
June 7 | r5 | TSC agreed to push M4-S and M5 out to June 14, concurrent with Sign Off. | M4-S, M5 | The TSC agreed that in the future we will combine M5 release readiness with Sign Off, rather than having separate milestones. |
May 24 | r4 | TSC approved M4, contingent upon review of PRs at the next TSC meeting | M4 |
|
Apr 19 | r4 | TSC approved revised schedule | M3, M4, M4-S | M3 slips two weeks. M4 and M4-S slip one week. Signoff stays the same. |
Mar 29 | r3 | TSC approved change to release process | M3, M4, M4-S |
|
Feb 1 | r2 | TSC approved M1 | M1 |
|
Dec 15 | r2 | Updated events, and Lakelse Sign Off | None |
|
Dec 14 | r1 | Approved by the TSC | all |
|
Dec 14 | r1 | second draft | M0, M1 | Moved kickoff to Jan 11 and M1 to Feb 1 |
Nov 1 |
| Initial draft | All |
|