Moselle Schedule
Anuket Project
Moselle Schedule
Revision: r5
Change Log
Date | Revision | Event / Change | Milestones Affected | Notes |
---|---|---|---|---|
June 21 | The TSC approved M4-S, M5, and Sign Off | M4-S, M5, Sign Off | ||
June 14 | TSC deferred M4-S, M5, and Sign Off to June 21 | M4-S, M5, Sign Off | ||
June 7 | r5 | TSC agreed to push M4-S and M5 out to June 14, concurrent with Sign Off. | M4-S, M5 | The TSC agreed that in the future we will combine M5 release readiness with Sign Off, rather than having separate milestones. |
May 24 | r4 | TSC approved M4, contingent upon review of PRs at the next TSC meeting | M4 | |
Apr 19 | r4 | TSC approved revised schedule | M3, M4, M4-S | M3 slips two weeks. M4 and M4-S slip one week. Signoff stays the same. |
Mar 29 | r3 | TSC approved change to release process | M3, M4, M4-S |
|
Feb 1 | r2 | TSC approved M1 | M1 | |
Dec 15 | r2 | Updated events, and Lakelse Sign Off | None | |
Dec 14 | r1 | Approved by the TSC | all | |
Dec 14 | r1 | second draft | M0, M1 | Moved kickoff to Jan 11 and M1 to Feb 1 |
Nov 1 | Initial draft | All |
, multiple selections available,
Related content
Moselle Release Progress
Moselle Release Progress
More like this
Lakelse Schedule
Lakelse Schedule
More like this
Pieman Schedule
Pieman Schedule
More like this
Red River Schedule
Red River Schedule
More like this
2022-05-18 - [Anuket Reference Model Workstream] Agenda and Meeting Minutes
2022-05-18 - [Anuket Reference Model Workstream] Agenda and Meeting Minutes
More like this
2022-03-07- [Anuket RA-1]- Workstream Meeting Agenda and Minutes
2022-03-07- [Anuket RA-1]- Workstream Meeting Agenda and Minutes
More like this