Moselle Schedule

Anuket Project

Moselle Schedule

Revision: r5

 

Change Log

Date

Revision

Event / Change

Milestones Affected

Notes

Date

Revision

Event / Change

Milestones Affected

Notes

June 21

 

The TSC approved M4-S, M5, and Sign Off

M4-S, M5, Sign Off

 

June 14

 

TSC deferred M4-S, M5, and Sign Off to June 21

M4-S, M5, Sign Off

 

June 7

r5

TSC agreed to push M4-S and M5 out to June 14, concurrent with Sign Off.

M4-S, M5

The TSC agreed that in the future we will combine M5 release readiness with Sign Off, rather than having separate milestones.

May 24

r4

TSC approved M4, contingent upon review of PRs at the next TSC meeting

M4

 

Apr 19

r4

TSC approved revised schedule

M3, M4, M4-S

M3 slips two weeks.  M4 and M4-S slip one week. Signoff stays the same.

Mar 29

r3

TSC approved change to release process

M3, M4,

M4-S

  • New milestone added (M4-S)

  • "Specification created" task moved from M3 to M4

  • "Proofreading" task moved from M4 to M4-S

  • Dates for existing milestones unchanged

Feb 1

r2

TSC approved M1

M1

 

Dec 15

r2

Updated events, and Lakelse Sign Off

None

 

Dec 14

r1

Approved by the TSC

all

 

Dec 14

r1

second draft

M0, M1

Moved kickoff to Jan 11 and M1 to Feb 1

Nov 1

 

Initial draft

All