Orinoco Schedule
Milestone | Description | Jan | Feb | Mar | Apr | May | Jun | Jul |
|---|---|---|---|---|---|---|---|---|
M0 | Kick Off | Jan 10, 2023 |
|
|
|
|
|
|
M1 | Release Definition |
| Feb 1, 2023 |
|
|
|
|
|
M2 | Scope Freeze |
|
| Mar 1, 2023 |
|
|
|
|
M3 | RC Validation Testing |
|
|
| Apr 4, 2023 |
|
|
|
M4 | RI Validation Testing / Content Freeze |
|
|
|
| May 2, 2023 |
|
|
M4-S | Proofreading |
|
|
|
|
| Jun 27, 2023 |
|
M5 | Release Readiness |
|
|
|
|
|
| Jul 25, 2023 |
M5 | Sign Off |
|
|
|
|
|
| Jul 25, 2023 |
Change Log
Date | Revision | Event / Change | Milestones Affected |
|---|---|---|---|
Jun 27, 2023 | 2 | M4-S approved. M5 moved to Jul 25, 2023 | M4-S M5 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|