Pieman Schedule

Anuket Project

Pieman Schedule

Milestone

Description

Delta in weeks

Date

Milestone

Description

Delta in weeks

Date

M0

Start of release

0

Oct 24, 2023 

M1

Release Definition

M0 + 2w

Nov 28, 2023 

M4

Content Freeze

M3 + 5w

Apr 9, 2024 

M4-S

Proofreading

M4 + 1w

Apr 16, 2024 

M5

Release Readiness

M4-S + 4w

May 14, 2024 

Change Log

Date

Revision

Event / Change

Milestones Affected

Date

Revision

Event / Change

Milestones Affected

Aug 9, 2023 

1

Creation of schedule

M0, M1, M2, M3, M4, M4-S, M5

Oct 10, 2023 

2

Update based on the assumption that Orinoco will be signed off on Oct 17, 2023 

M0, M1, M2, M3, M4, M4-S, M5

Oct 17, 2023 

3

Update based on the assumption that Orinoco will be signed off on Oct 24, 2023 

M0, M1, M2, M3, M4, M4-S, M5

Nov 28, 2023 

4

Approval of M1, skipping of M2

M1, M2

Dec 5, 2023 

5

Skipping M3 as there are no implementation projects.

M3

Mar 19, 2024 

6

Moving M4 to Apr 9, 2024  and delay all following milestones with 2 weeks

M4, M4-S, M5