OPNFV TSC Meeting 2020-09-15

Anuket Project

OPNFV TSC Meeting 2020-09-15

Date

Sep 15, 2020   

link https://zoom.us/j/99523505422?pwd=bzhUd1E3M1BnQnBad3VuS0NnNkQwZz09

Attendees

  • @Al Morton

  • @Former user (Deleted)

  • @Frank Brockners

  • @Qiao Fu

  • @Trevor Cooper

  • @Mark Beierl

  • @Emma Foley

  • @Lincoln Lavoie

Absent

  • @Georg Kunz

  • @Former user (Deleted)

  • @Sridhar Rao

  • @Sunku Ranganath (Deactivated)

Non TSC Attendees

  • Add as needed

Agenda items

Time

Item

Who

Notes

Time

Item

Who

Notes

5 min

Meeting Admin

Agenda Bashing
Attendance/Quorum (8/7)
Approval of Meeting Minutes: Agenda - 2020-09-08 and IRC Meeting Minutes

@Al Morton



5 min

Announcements

Fall Technical Event - Not the same week as ONES!

Volunteer(s) needed to run the OPNFV Weekly Technical Discussion meetings: ASAP - rotating chairs, see right-hand column

@Al Morton

Sept - @Sridhar Rao

Oct - @Emma Foley

Nov -

Dec -

15 Min

Recording for the purpose of audio transcript only. 

@Mark Beierl



1 min

Docker image retention policy

@Trevor Bramwell

Aug 31, 2020 Tech Discuss meeting

Sep 9, 2020 TAC Meeting Agenda

15 min

OPNFV Release Process

Status

 

@Al Morton

@David McBride

Partial list of issues discussed:

  1. Are the Definitions of Gates clear?

    1. Testing of the CNTT-selected RC Test Cases

    2.  projects must pass Gating (s 17)

    3. Gates need to be established, install without errors, simple functional tests, success of more advanced features and automated with X-testing

  2. Pre-requisites, include Integration TEST project (Morgan in ONAP), test what OPNFV delivers.

  3. OPNFV needs to Release and Support tests that are reliable.

    1. "Establish" items are the key steps for TSC: Requirements Vetting and Integration Test SCs





10 min

CNTT Engagement status updates

Release Naming - CNTT in 2021?

@Jim Baker @Scot Steele



10 min

2021 Budget
  • Marketing and HW buckets, CAPEX, LF Staffing

  • SLIDES !!  Like last year, increase or decrease, or just right!

  • #agree on modified "goldylocks" budget slide Sep 1, 2020 

  • Detail Gathering complete (@James Gu , others)

  • Some TAC reps proposing more detailed usage review

@Jim Baker

SEPTEMBER 8 DEADLINE!!!!!

OPNFV LFN 2021 Gathering Project Input (3).pdf

5 min

OVP Engagement status update

 recent status update



@Trevor Cooper

@Lincoln Lavoie



5 min

Gitlab Pilot

Review the pilot plans and timing

@Trevor Bramwell



2 min

OPNFV Project Reviews

Projects:

@Jim Baker

@Trevor Cooper Project code being used in Akraino and another project. PTL not responding. Some interest in moving the repo to Akraino

Start new review round at Virtual Technical Meetings, 10 minute talks:  sign-up now!

Oct 13, 2020 

10 min

Status Updates

OPNFV Linux Foundation Lab (Portland) hardware upgrade status
LF IT/Infra update: (Aric GardnerTrevor Bramwell)

@Jim Baker
@Trevor Bramwell





5 min

Future Topics

Future Topic: new template for staffing task & requirement evaluation - similar to Intern projects @Mark Beierl
Future Topic: Yardstick's future??  HA test cases.  Bottlenecks' Stress test spawns VMs till it breaks in OVP



  • new template concept is on hold